Allahabad Bypass Project (ABP-3)

Contract Section

:

Ch.220.354 (Bagaikala) to Ch. 242.708 (Handia)

Employer

:

National Highway Authority of India

Engineer

:

LASA

Contract Limit

:

22 Km

Contract Agreement

:

4 - Nov - 04

Original completion date

:

4 - May - 07

Revised Completion date

:

4 - May - 07

Final contract Price

:

Rs. 2,526,353,607/-

Payable INR

:

Rs. 2,273,718,247/-

US Dollar

:

$ 55,390,34.00 (US$=Rs.45.61)