SH-17 (Bangalore - Mysore Road)BM-2

Name of the work

:

SH-17 (Bangalore - Mysore Road) BM-2

Employers

:

KRDCL

Engineer

:

LEA

Project Started Date

:

21-04-2004

Project Completed Date

:

21-12-2005

As per the programme Completion date

:

30-06-2005

Project Started From

:

CH - 51+200 (RAMNAGAR)

Project Ending At

:

CH - 82+500 (MADDUR)

Project Length

:

28.800KMS

Project Cost

:

103.32Crs